Morning Call: June 15, 2004
As work nears an end on the new northbound Route 33 bridge over a sinkhole-prone
stretch of Northampton County, transportation officials announced
Monday that the state will close and dismantle the adjacent southbound
bridge.
State Transportation Secretary Allen D. Biehler said the southbound
bridge, which has carried traffic in both directions since a sinkhole
forced demolition of the northbound bridge five months ago, remains
safe for motorists. But it will close around the Fourth of July, when
the northbound bridge is scheduled to open.
The state Department of Transportation decided last week to dismantle
the southbound bridge because it would be safer, easier and quicker,
albeit a little more expensive, to build and anchor a new span at a
cost of $3.3 million, rather than anchor the existing structure to solid
rock 310 feet below the surface -- 5 feet more than the height of the
Statue of Liberty.
"The southbound side is good," Biehler said in a telephone
interview. "It's not at risk of falling in. But that's not to say
if we don't see a risk, we will not shut it down tomorrow. It's very
unusual geology in that section of Pennsylvania."
The original northbound bridge sank 6 inches on Jan. 24 after a sinkhole
undermined a pier on a Bushkill Creek bank below. After failing to fill
the sinkhole, PennDOT removed the bridge, and the federal government
agreed to cover 90 percent of the cost.
The southbound bridge then dipped 1 inch between Jan. 25 and Feb. 26,
and PennDOT engineers do not know why. Biehler said it has not moved
since and is constantly monitored.
When the southbound bridge is closed, traffic will not be detoured
through residential neighborhoods. Like northbound motorists now, southbound
drivers will be routed a short distance over crossovers to be built
over the grassy median to the passing lane of the other bridge, Biehler
said.
Unlike the closure of the northbound bridge, he said, no highway exits
will be affected. The north Route 191 exit, closed since February, will
reopen when the north bridge is finished.
"There's some additional costs involved of about 10 percent, but
the construction time will be shortened, and it provides a permanent
fix to the bridge problem," state Rep. Craig Dally, R-Northampton
said.
PennDOT spokesman Ron Young said the original cost estimate was $6.5
million, which included the emergency work and retrofitting the south
side. He said the actual cost for the northbound bridge is $3.5 million,
and the south bridge should be cheaper because the same design is being
used.
Biehler said he has spoken to the U.S. Department of Transportation
about covering any additional costs. If the federal government balks,
he said, state dollars will be used.
A retrofitted southbound bridge would have cost $3 million and been
finished by New Year's Day, Biehler said, but a new bridge will cost
$3.3 million and be completed by Thanksgiving.
It was a cost and time differential that Dally and other area legislators
could live with.
"I believe the costs associated with that are reasonable when
you consider the nature of the problem is one of geology," said
Sen. Rob Wonderling, R-24th District.
The northbound bridge, originally scheduled to open in September, is
now expected to be completed by the end of the month, or July 4 at the
latest, said Sen. Lisa Boscola, D-Northampton.
"I'm so used to PennDOT mostly doing patch up, doing what it takes
to get traffic moving," she said. "But this goes beyond patch
work."
PennDOT had originally planned to shore up the south bridge's piers
by connecting them to bedrock. But, Biehler said, it would have been
too dangerous for construction crews and motorists. He said a 40-foot
crane would have had to be parked on the bridge to drill through the
span's deck to solid rock in the creek area underneath, and the drilling
could possibly cause sinkholes by disturbing the porous underground
limestone.
PennDOT is building the new bridges without piers to avoid the unstable
creek, which is pocked with sinkholes along the Palmer Township-Stockertown-Tatamy
borders.
When both Route 33 bridges, which straddle the Bushkill in Palmer Township,
were built in the early 1970s, they were not anchored into solid rock.
Biehler said
PennDOT still does not know why the spans were built that way except
that it was standard practice then.
Steve Esack