Morning Call: September 25, 2004
Due to newsroom front-end system production difficulties the entire
text could not be electronically captured for the online archive, please
see microfilm for complete map.
For the first time, a state official Friday publicly blamed a Stockertown
quarry for contributing to a rash of sinkholes that has disrupted traffic
and damaged private property in parts of Northampton County for four
years.
But Gary Hoffman, deputy secretary of operations for the state Department
of Transportation, stopped short of blaming Hercules Cement Co. for
a sinkhole that damaged a northbound Route 33 bridge in January and
led to its $3.5 million replacement as well as the state's decision
to replace the southbound bridge.
Hoffman said it was PennDOT's fault the northbound bridge over the
Bushkill Creek failed because the state did not take into account the
region's porous geology when the span was built in the 1970s.
"We know that the quarry is unquestionably a contributor,"
Hoffman told residents and government officials at Memorial Library
of Nazareth and Vicinity. "But to say it is 50 percent, 60 percent
of the problem or 90 percent of the problem, I think none of us can
say that."
Hercules officials did not attend the meeting, which elected officials
called to brief residents on an 8-month-old joint state and federal
probe into the sinkholes and a new plan to slow sinkhole development
in and around the Bushkill.
Joe Pospisil, Hercules' vice president of manufacturing, could not
be reached. However, he has said there is no proof that the 98- year-old
company is responsible because sinkholes form naturally in limestone-rich
regions. Two other Nazareth area quarries -- Essroc
Italcementi Group and Eastern Industries Inc. -- have made the same
argument.
The sinkhole plan, which residents oppose and is being reviewed by
the state Department of Environmental Protection and U.S. Army Corps
of Engineers, calls for Hercules and PennDOT to jointly line 850 feet
of the creek, up to the state-owned land around the Route 33 bridges,
with a synthetic material.
The state hopes the plastic membrane, which Hercules has a separate
permit to use at two other stream locations farther north, will stop
creek water from draining into the ground and causing sinkholes. The
lining would then reduce the amount of creek water flowing underground
through sinkholes and into the quarry.
Hoffman said he knows the lining won't solve the overall sinkhole problem,
but it's the best short-term solution to protect the bridges. He added
the lining would help protect the creek if the Corps receives federal
approval and local or state assistance to line more of the stream bed.
However, he said, if the joint plan is approved, PennDOT would not
begin its share of the work if studies show the lining would have a
detrimental effect on residents downstream of Route 33.
In not blaming Hercules for the sinkhole under the Route 33 bridge,
Hoffman said sinkholes have been opening in the area for generations.
"Those bridges should have been on deep foundations to begin with,
but that is literally water down the hole now," Hoffman said. "There
were probably sinkholes developing out there before the quarry. There's
going to be sinkholes developing if the quarry went away."
Studies have shown that quarries can cause sinkholes when they pump
groundwater out of their pits. The pumping creates a massive underground
funnel called the "cone of depression" or "zone of influence."
Groundwater is sucked up through the cone, which then buckles the surface
above until a hole opens.
Based on Hercules' own groundwater studies, which DEP uses as its official
records, the quarry's cone is believed to cover 2.2 square miles, stopping
on the east side of the northbound Route 33 bridge. The studies estimate
Hercules' cone will grow an additional 1.3 square miles when the quarry,
now 300 to 330 feet deep, uses DEP's March 2003 approval to mine deeper.
Although state officials previously acknowledged the size of Hercules'
cone, no one said Hercules has contributed to the sinkholes, which began
opening in 2000 when a Palmer Township family was forced from their
home and the small Stockertown-Tatamy bridge was swallowed.
DEP mining inspector Mike Menghini said Friday that although the state
granted Hercules' a "conditional approval" to mine an additional
150 feet, the agency is now having second thoughts.
"We are not comfortable with them going deeper. We want them to
go laterally," Menghini said. "We could stop [the permit]
if it shows an effect they cannot remediate, but then they can appeal
that."
Steve Esack